PROJ / 001INFRASTRUCTURE

West Permian Cogen & Switchyard
Reeves Co., TX2024$684M







Greenfield 480MW cogen built on collapsible-soil terrain with a hard-stop tie-in window to the regional grid — 31 months from NTP.
Dynamic compaction across the foundation pad, self-performed concrete and rebar (62k CY), and parallel pre-fab of structural skids to compress mechanical erection.
Energized on the contractual grid window. 0.00 TRIR across 2.4M field hours. 4.2% under guaranteed maximum price.